Construction of phase 1 (Tarlac City to Rosales) Tarlac–Pangasinan–La Union Expressway
1 construction of phase 1 (tarlac city rosales)
1.1 tarlac city–pura segment opening
1.2 pura–ramos segment opening
1.3 ramos–carmen/rosales segment opening
construction of phase 1 (tarlac city rosales)
approaching victoria exit. first phase (tarlac city–victoria–pura) opened motorists in november 2013
the first phase of tarlac-la union toll expressway started in january 2010.
the new tplex logo part of smc infrastructure
in april 2013, san miguel corporation announced segment tarlac city urdaneta built 4 lanes, instead of initial plan of 2 lanes only. however, pushed opening day of expressway june 2013 november 2013.
tarlac city–pura segment opening
on october 25, 2013, toll regulatory board authorized issuance of toll operation permit tarlac city–pura segment of tplex after construction of segment completed private infra dev corp. (pidc), all-filipino consortium backed conglomerates san miguel corp. (smc) , dmci holdings inc.
this first phase, referred section 1a, begins connection sctex, stretches 17 kilometres (11 miles) tarlac city victoria, , pura, tarlac. expected cut current travel time baguio as 40 minutes.
pura–ramos segment opening
on december 23, 2013, expressway opened ramos, tarlac, bringing tplex 23 kilometres (14 mi) of operational length.
ramos–carmen/rosales segment opening
on april 16, 2014, phase 1 of project completed when rosales section opened in time lenten traffic , halfway go baguio.